September 4, 2006

New Reference Desk
The new reference desk is installed

Carpet laying
Carpet laying continues into the reference area

September 11, 2006

New Reference Desk
Carpeting work continues into the reference and computer area...

Carpet laying
...and the north seating area

September 18, 2006

Children's room prepared
Carpeting and shelving is removed from the Children's Department in preparation for asbestos abatement

Parking lot work
A large water truck is brought in to assist in the parking lot work

September 18, 2006

Temporary home
The Children's Department moves into their temporary home in the auditorium

children's computers in classroom
The children's computers are temporarily housed in the new computer classroom near the reference desk

September 18, 2006

Children's Department prepares to move
Children's Department prepares to move

Department is stripped
The children's desk is removed and a temporary wall goes up 

September 25, 2006

Memory bricks
Work begins on a commemorative brick wall

Parking lot work
Layers of asphalt are removed from the rear parking lot